Decision to enter into a Grant Funding
Agreement for £102m of funding for the CSLR from the Housing
Infrastructure Fund and to accept the funding into the Capital
Programme.
Decision type: Key
Reason Key: Expenditure > £500,000;
Decision status: For Determination
Divisions affected: (All Divisions);
Notice of proposed decision first published: 28/06/2019
Anticipated restriction: Public -
Decision due: 23 Jul 2020 by Cabinet
Lead member: Cabinet Member for Highways and Transport
Lead director: Executive Director - Economy and Infrastructure
Department: Economy and Infrastructure
Contact: Angela Jones, Executive Director - Economy and Infrastructure Cumbria House, 117 Botchergate, Carlisle CA1 1RD Email: angela.jones@cumbria.gov.uk.
Consultees
Public and Stakeholder Consultation –
January to March 2018
Landowners ongoing engagement – Since August 2017 to Project
Completion (March 2023)
Public and Stakeholder Consultation – 31 May to 12 July
2019
Relevant Scrutiny Committee / Advisory Board: Scrutiny Advisory Board - Communities and Place