Decision to enter into a Grant Funding
Agreement for funding for the Carlisle Station Gateway Project from
the Borderlands Inclusive Growth Deal and to accept the funding
into the Capital Programme.
Decision type: Key
Reason Key: Expenditure > £500,000;
Decision status: For Determination
Divisions affected: (All Divisions);
Notice of proposed decision first published: 11/12/2020
This decision will be taken under urgency procedures.
Reason for urgency:
It is impractical to defer the decision until it can be included in the next Forward Plan as there is an urgent need to get the funding agreement in place to allow Cumbria County Council to accept the funding to allow the project to commence.
Anticipated restriction: Public -
Decision due: 17 Dec 2020 by Cabinet
Lead member: Leader of the Council
Lead director: Executive Director - Economy and Infrastructure
Department: Economy and Infrastructure
Contact: Angela Jones, Executive Director - Economy and Infrastructure Email: angela.jones@cumbria.gov.uk.
Consultees
Public and Stakeholder Consultation –
January to March 2018
Landowners ongoing engagement – Since August 2017 to Project
Completion
(March 2023)
Public and Stakeholder Consultation – 31 May to 12 July
2019
Relevant Scrutiny Committee / Advisory Board: Scrutiny Advisory Board - Communities and Place